Topics
All topics

Commercial

Contracts and BOQ

Subcontract, bill of quantities, Form №2 import, advance, retention, penalty, the contract document and change orders.

Opening a contract

  1. 1In Contracts click "Add"; search for the subcontractor (if not registered, its company is created).
  2. 2Enter the title, amount, currency, retention rate and end date.
  3. 3Enter the daily delay penalty, the advance amount and the advance recovery rate.
  4. 4Tick whether the subcontractor supplies materials: material requests from the schedule are routed accordingly.

Bill of quantities

The BOQ holds unit-priced items in sections; the price has three components: material, labour and machinery. Payments, schedule splitting and material calculation all work from these items. If a recipe is linked to an item, work entries deduct materials from stock.

Form №2 import

An existing Georgian Form №2 (.xlsx) file is imported: sections, items, price components, party details and the work done to date are read. Before importing, the header fields (parties, contract no/date, overhead %, profit %, VAT %) can be corrected in the preview; a field left blank does not erase the existing value.

Contract document

The "Contract" button generates a Word/PDF document (Turkish, English and Russian templates are ready; for Georgian the company's own text). The document is sent to the subcontractor for approval; the owner or admin approves or rejects with a reason. Every version stays in the history. This is an approval record, not an electronic signature.

Change orders

Work not in the contract, or changed work, is recorded with a change order: items, cost impact (+/−), time impact (days) and attachments. Once approved, new items are added to the BOQ as an "EXTRA" section; the quantity of an existing item can also be revised (not below the paid quantity). The time impact of approved orders is added to the end date for the delay penalty.

Consumption recipe

A recipe is linked to a BOQ item as its 'Consumption recipe' when editing the item. It is not shown in Form №2 or the BOQ list; it is used only for stock deduction and the write-off act. Work entries without a takeoff link (including those entered from the Form №2 table) also deduct stock automatically with it, and editing an entry recalculates the deduction.

Related module pages

Sign in with the demo account to try it

In the demo company every screen in this guide is filled with sample data; it is reset every night.

[email protected] · Demo12345!

Subcontractor account: [email protected] · Demo12345!

Independent subcontractor account (two employers): [email protected] · Demo12345!