Activities, links, work calendar, critical path, baseline, resources and floor-by-floor scheduling from the BOQ.
Activities and progress
An activity is entered with a name, phase, block, planned dates, responsible contract and an optional start time. The status is not typed but derived: planned, in progress, completed or delayed.
Progress comes from three sources: a manual percentage, unit work items in a linked category, or work entries on the BOQ item linked to the activity (relative to the target quantity).
Links and critical path
Activities are linked with FS (finish-to-start), SS, FF and SF links, with lag days. The critical path calculation finds each activity's float; activities with zero float are marked critical.
Work calendar
In the calendar dialog you choose the working weekdays (e.g. Monday–Saturday) and holidays; Georgian public holidays (including Orthodox Easter) are added in one click. With a calendar defined, durations, float and the critical path count working days only.
Resources
Write the resources each activity needs (e.g. 6 formworkers, 1 crane). The weekly resource load table shows, for each week, the people and equipment needed at the same time on the busiest day; the peak week is red.
Splitting a BOQ item across floors
A large contract item (e.g. 300 m³ of concrete) is split into equal parts, creating a separate activity per floor; each part is linked to the finish of the previous one. A work entry made on that activity on site advances it and counts the same quantity towards the BOQ item and the payment.
- 1In the schedule click "Split from BOQ".
- 2Choose the contract and BOQ item; if part of it was already split, the remainder is suggested.
- 3Enter the number of parts, the start and the duration; check the preview.
- 4Create; the activities are added to the schedule as a chain.
Material needs from the schedule
For an activity linked to a BOQ item and a target quantity, "Calculate material needs" works as: item recipe × quantity (incl. waste) − site stock − requests already opened = shortage. Purchase requests are opened for the shortage; for a contract where the subcontractor supplies materials the request goes to the subcontractor's list, otherwise to the developer's. Running it again does not create duplicates.
Related module pages
Sign in with the demo account to try it
In the demo company every screen in this guide is filled with sample data; it is reset every night.