Topics
Site
Drawings, revisions and approval
Uploading drawings, the revision chain, drawing types, technical office approval codes A/B/C/D and distribution to site.
Upload and revisions
A drawing is uploaded with a name, discipline (architectural, structural, mechanical, electrical…), revision code, date, note and file (PDF, DWG, image), and linked to a unit, a zone or the whole project. A file uploaded with the same name and discipline becomes the new revision of that drawing; older ones stay in the history.
Drawing type
Each revision has a type: tender/permit, issued for construction (IFC), shop drawing and as-built. A tender drawing uploaded by the developer is for information only (Code D); an IFC drawing is valid immediately.
Approval codes
A drawing uploaded by a subcontractor enters "awaiting approval" and is not distributed to site until the technical office approves it. Only the owner, admin or site manager on the developer side can review:
- 1Code A · Approved: work on site can start immediately.
- 2Code B · Approved with comments: build following the notes; fix in the next revision.
- 3Code C · Rejected: construction is forbidden; a reason is required and it must be revised and re-uploaded.
- 4Code D · For information: no approval needed, for coordination.
Current revision
A drawing's current revision is the newest Code A or B. When a new revision is approved, the previous ones get the "SUPERSEDED · old revision" label so nobody on site works from an old sheet. QR cards show only current A/B drawings.
When a buildable revision is issued, work items in the related units are flagged, an instruction and an announcement are opened and a notification is sent.
Related module pages
Sign in with the demo account to try it
In the demo company every screen in this guide is filled with sample data; it is reset every night.
[email protected] · Demo12345!
Subcontractor account: [email protected] · Demo12345!
Independent subcontractor account (two employers): [email protected] · Demo12345!