Work done and quantity entry
How a single work entry updates progress, stock and the payment; the Form №2 worksheet.
One entry, three effects
Work Done is the site's daily production record: "Block A 3rd floor screed, 48 m²". When the entry is linked to a takeoff item and the contract's BOQ item, three things happen automatically:
1) Progress of the takeoff and the schedule activity is updated. 2) The materials in the item's recipe are deducted from stock. 3) The quantity is written to the contract's next payment as "this period".
Making an entry
- 1In Work Done click "Add entry"; choose the date and location (unit/zone).
- 2Choose the contract and BOQ item. If this unit has a takeoff linked to that item it is picked automatically and the quantity is filled with the remaining amount.
- 3Pick the schedule activity if there is one; the entry advances the activity.
- 4Enter the quantity, a photo and equipment hours if needed, and save; the effects are summarised on screen.
Form №2 worksheet
On desktop the contract's BOQ opens in a wide table in the Form №2 layout: contract quantity, previous cumulative, this period and remaining for each item. At period end the subcontractor can enter quantities row by row from this table; each row becomes a work entry.
Late entries
Entries dated in a closed period but made after the last payment are not lost: they are included in the next payment, and their count is shown with a "late entry" warning.
Recording without internet
If there is no connection on site the form still saves; the entry waits on the phone and is sent automatically when the connection returns. See the Mobile and offline guide for details.
Related module pages
Sign in with the demo account to try it
In the demo company every screen in this guide is filled with sample data; it is reset every night.
[email protected] · Demo12345!
Subcontractor account: [email protected] · Demo12345!
Independent subcontractor account (two employers): [email protected] · Demo12345!