Progress payments
Calculating the period payment, deductions (penalty, defects, advance, retention), partial approval, retention release and outputs.
How is a payment calculated?
"Payment from work done" sums the work entries linked to BOQ items up to the period end and subtracts the cumulative amount paid in previous payments; remaining quantity × unit price is this period's amount. Quantity over the contract is shown with a warning and not paid.
The Georgian Form №2 chain is applied: items → overhead → profit → VAT → grand total. Then retention, penalty and advance recovery are deducted and the net payable results.
- 1In Finance choose the contract, click "Payment from work done" and pick the period end.
- 2Check the item table; correct the "this period" quantity by hand if needed.
- 3Review and apply the deduction suggestions.
- 4Create the payment; its status moves draft → submitted → approved → paid.
Delay penalty and extension of time
The daily penalty only applies after the contract end date has passed. Two things are added to the end date: days marked "work halted" in the site diary and the time impact of approved change orders. Each payment counts only the delay days falling in its own period; the same day is never penalised twice.
Defects not fixed by their due date carry no daily penalty; the actual repair cost entered on the defect is deducted once. Overdue instructions are listed for information and are not penalised.
Advance and retention
If the contract has an advance, each payment automatically suggests the recovery rate × gross; it never exceeds the remaining advance and can be changed by hand.
Retention is withheld from each payment at the contract rate. Withheld, released and held retention are summarised; "Retention release" creates a release payment that goes through the normal approval and payment flow.
Partial approval
On a submitted payment the developer can reduce this period's quantity of disputed items and write a reason (it cannot be increased). Overhead, profit, VAT and net are recalculated; the quantity the subcontractor claimed stays on record. The payment is then approved.
Outputs
Every payment downloads as PDF and as Georgian Form №2 Excel. The same payment can also be produced in other countries' layouts: KS-2 / KS-3 and the Turkish progress payment format (Excel or PDF). For accounting, the period's transactions are exported to Excel separately. Exchange rates come from the official rate of the National Bank of Georgia.
Material write-off act
'Write-off act' on each payment row puts into one document the materials of the period's work by consumption recipe (norm, waste, total), the quantity actually deducted from stock in the same period, the difference and the amount. It has director approval, commission and signature lines; Excel or PDF, in the interface language or Georgian.
Related module pages
Sign in with the demo account to try it
In the demo company every screen in this guide is filled with sample data; it is reset every night.
[email protected] · Demo12345!
Subcontractor account: [email protected] · Demo12345!
Independent subcontractor account (two employers): [email protected] · Demo12345!